JOHANNESBURG, South Africa (AFP) — South Africa's debt-laden State power company Eskom, on Monday announced it was implementing a more intense electricity rationing schedule, five days after continued rolling power cuts have plunged businesses, schools and homes into darkness.

The power cuts, known as load shedding, are implemented to prevent a collapse of the electricity grid. They were previously implemented in February and again in October.

The embattled, State-owned utility Eskom, which generates around 95 per cent of the country's electricity, has long struggled to produce power – due to ageing infrastructure at its coal-fired power stations and decades of mismanagement.

To date, load shedding had been implemented only up to what is known as stage 4.

But on Monday Eskom announced it had moved to stage 6 load shedding as from 6:00 pm (1600 GMT), which requires 6000MW to be rotationally load shed as a result of a capacity shortage.

“This follows a technical problem at Medupi Power Station impacting additional generation supply,” Eskom said in a statement.

“The heavy rains has caused coal handling and operational problems at several power stations,” it said, adding that its technical teams would be working through the night to restore units.

The latest wave of power cuts comes two weeks after the International Monetary Fund warned that reliance on Government spending to boost growth, coupled with continuous bailouts to State-owned entities was not sustainable.

One of the biggest risks to the economy, according to pundits, has been posed by the embattled State power company Eskom, which has a 450 billion rand (US$30 billion) in debt despite multiple bailouts from the State.

Government plans to pour 128 billion rand (around US$8.8 billion) into Eskom over a three-year period that began in February 2019.

President Cyril Ramaphosa on Monday acknowledged that the problems with the construction of Medupi and its 'twin', Kusile station account for much of the financial crisis at Eskom.

“The cost of building the power station has escalated dramatically since it's building started. It is behind schedule and — with five of its six units now in commercial operation — it is not yet performing at the level it is expected to perform,” he said in a statement.

In November, the company announced a new CEO in Andre de Ruyter to turn around the entity, after Phakamani Hadebe resigned in July citing “unimaginable demands” of the job.

But Eskom also warned of a further hefty annual loss and a rise in debt, to the equivalent of US$30.8 billion, in the fiscal year that ends on March 31, 2020.

Pressure has been mounting for Ramaphosa – who was re-elected this year in part on a pledge to restore the economy.

He has announced plans to divide Eskom into three subsidiaries: generation, transmission and distribution, by March 2020.


Now you can read the Jamaica Observer ePaper anytime, anywhere. The Jamaica Observer ePaper is available to you at home or at work, and is the same edition as the printed copy available at http://bit.ly/epaperlive


ADVERTISEMENT




POST A COMMENT

HOUSE RULES

1. We welcome reader comments on the top stories of the day. Some comments may be republished on the website or in the newspaper � email addresses will not be published.

2. Please understand that comments are moderated and it is not always possible to publish all that have been submitted. We will, however, try to publish comments that are representative of all received.

3. We ask that comments are civil and free of libellous or hateful material. Also please stick to the topic under discussion.

4. Please do not write in block capitals since this makes your comment hard to read.

5. Please don't use the comments to advertise. However, our advertising department can be more than accommodating if emailed: advertising@jamaicaobserver.com.

6. If readers wish to report offensive comments, suggest a correction or share a story then please email: community@jamaicaobserver.com.

7. Lastly, read our Terms and Conditions and Privacy Policy



comments powered by Disqus
ADVERTISEMENT

Poll

ADVERTISEMENT
ADVERTISEMENT

Today's Cartoon

Click image to view full size editorial cartoon
ADVERTISEMENT