Rules behind the rebuild
Everything you need to know about the proposed new procurement framework for NaRRA
Beyond the heavy equipment, construction sites, and damaged infrastructure, another part of Jamaica’s post-Hurricane Melissa recovery is taking shape in Parliament: the rules that will determine how reconstruction contracts are awarded.
During last week’s sitting of Parliament, Finance Minister Fayval Williams opened debate on a special procurement system for the National Reconstruction and Resilience Authority (NaRRA) and accompanying regulations intended to speed up decisions when contractors challenge procurement awards.
At the heart of the proposals is a major change in how NaRRA will spend public money. Rather than follow most of the usual procedures under the Public Procurement Act, the authority will operate under a separate set of rules, with different spending thresholds, fewer approval layers, and greater flexibility in selecting contractors.
The Government says the changes are necessary because the scale of Jamaica’s post-Hurricane Melissa reconstruction effort requires a procurement system that can move more quickly than the one designed for routine Government spending.
Under the existing public procurement system, Government contracts generally go through several stages of approval intended to ensure public money is spent properly and contractors are selected fairly.
Williams argued, last Tuesday, that while those procedures are suitable for ordinary Government spending, they could slow a large reconstruction programme involving several projects that need to be carried out at the same time.
She said delays in awarding one contract could affect other projects that depend on it, while unexpected problems at damaged sites might require changes to plans and technical solutions.
Williams noted that the Government was seeking a middle ground that would allow NaRRA to work more quickly while retaining safeguards against fraud, collusion, unfairness, and the misuse of public money.
She also explained that the existing emergency procurement provisions under the Public Procurement Act were not designed for a prolonged reconstruction programme. Amendments passed in 2025 allow emergency contracts in specified circumstances, including disasters and extreme urgency, but require public notice of those contracts within one month of their award. The notice must identify the contractor, contract value, and circumstances that justified the emergency award.
Williams said that emergency route was intended for short, exceptional situations, rather than the scale of work expected under NaRRA, the statutory body established by the Government this year to coordinate and execute reconstruction and resilience projects following the devastation unleashed by Hurricane Melissa on sections of the island in October 2025.
The proposed order would exempt NaRRA from most of the Public Procurement Act, subject to conditions set out in the order. However, some existing protections would remain in place. Part VI of the Act, which allows suppliers who believe they have been unfairly treated to request a review of procurement decisions, would continue to apply, along with the Public Procurement (Reconsideration and Review) Regulations, 2018, which set out the procedures for challenging those decisions.
One of the main changes concerns the value of contracts and the level of competition required.
Under the proposed system, single-source procurement could be used for contracts valued below $10 million. This means NaRRA could select a supplier without inviting competing bids, subject to the requirements of the order.
For contracts valued at $10 million or more, but below $250 million, restricted competition could be used. This involves inviting suppliers from NaRRA’s qualified pool to submit bids.
Contracts valued at $250 million and above would generally be subject to open competition, allowing suppliers to compete more widely.
The order would also allow NaRRA to use methods such as requests for bids, quotations and proposals, competitive dialogue, and framework agreements. The framework agreements would allow the authority to agree on terms with suppliers in advance so that frequently needed materials, such as cement and steel, could be ordered more quickly.
The proposed rules would also change the approval process for large contracts.
NaRRA would be able to award contracts below $500 million without Cabinet approval. Contracts valued at $500 million or more, but below $1 billion would require prior Cabinet approval, while contracts valued at $1 billion or more would require both Cabinet approval and independent assurance.
Independent assurance involves an assessment by a suitably qualified person or firm separate from NaRRA and the contractor. It would help determine whether the proposed contract price is reasonable.
The proposed system would also remove the separate approval of the Public Procurement Commission for NaRRA contracts. However, a procurement committee appointed by the authority’s chief executive officer would conduct checks before contracts are awarded, including whether the correct procedures were followed and bids were assessed using the criteria disclosed to suppliers.
The Government is also seeking to ensure that local businesses benefit from the reconstruction programme.
Under the proposed order, NaRRA could give Jamaican micro, small and medium-sized enterprises a 15 per cent preference during bid evaluation, and other Jamaican suppliers a 10 per cent preference, where a foreign bidder is competing and the required local-content conditions are met.
Those conditions include a commitment to spend at least 25 per cent of the contract value on goods, materials, components, services, or labour originating from or made in Jamaica.
In addition, contractors undertaking alliance and works contracts valued at $500 million or more would generally be required to subcontract at least 15 per cent of the contract value to Jamaican suppliers.
Williams said NaRRA would also establish a capacity register to help businesses
— including small contractors that have never held Government contracts
— register their details and avoid repeatedly submitting the same documents.
Despite the proposed changes, Williams said NaRRA would still be required to follow rules intended to protect public funds and ensure fair treatment of suppliers.
Evaluation committees would have to assess bids using the criteria published in the procurement documents. Officials involved in the process would also have to declare conflicts of interest, while records would have to be kept of procurement decisions and the reasons for them.
NaRRA would also be able to publish contract award notices through an electronic procurement portal, identifying the successful contractor and the value of the contract. Publication could be delayed in specified circumstances, including national security and the protection of legitimate commercial interests.
Williams said the auditor general and the Integrity Commission would be able to review contracts awarded by the authority.
The second measure debated by Williams seeks to shorten the time the Procurement Review Board has to communicate its decisions in cases involving NaRRA.
Under the existing regulations, the board has up to 20 working days after a hearing concludes to communicate its decision in writing. The proposed amendment would reduce that period to 14 working days for NaRRA-related cases.
Williams said the shorter deadline was intended to prevent procurement disputes from unnecessarily delaying reconstruction projects. She said the rights of suppliers and other parties to seek reconsideration and review would remain in place.